PROJECT AUTHORIZATION |
PACKET ID: PMT-805V |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1615101D |
16151 |
0 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
066 042 1 021-022 |
|
11-08951 |
11-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
ROADWAY SAFETY-M&P |
0.0160 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
CONSULT |
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
|
STATE |
DOH |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
11-8951 |
D |
1100 |
FD04 |
|
2023 |
|
$520,000.00 |
CURRENT FUNDING REQUEST TOTAL: $520,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$520,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $520,000.00 |
THIS AUTHORIZATION PROVIDES INITIAL FD04 DESIGN FUNDS FOR THE PROJECT. |
|
Project Approval Recommended By:
James Ballinger 2/9/2023 |
Signed and Approved by:
Jim Gray 2/9/2023 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
11-08951.00 |
LESLIE
|
11 |
US-421 |
US 421 |
0.0160 MI |
CONSTRUCT RIGHT TURN LANE ON US 421 AT INTERSECTION WITH KY 80. (16CCN)(18CCN) (2022CCR) |